Contract: NEC 3 value: £6.9M Duration: 92 wks

Construction of a 132kV – 11kV Primary Substation within the Olympic Park.
Enabling works to remediate contaminated site, and construction of a 3 tier basement and 3 storey RC structure with brickwork cladding to house 3 no 90 ton transformers and related electrical switch gear and to supply power to the Olympic venues both during construction of the Olympic sites and the venues during the games. Also supply Stratford City Development (athletes village) and future legacy sites.